
Tshwane mayor gives update on Rooiwaal waste water plant
Loading player...
Cilliers Brink said the DBSA had been appointed as the implementing agent, and the contractor was appointed in September. “The site certificate has been issued [also in September], the site has been cleared [the work started in March], sediment basins are also cleared, and we are still building a fence to secure the area. We are basically ready to roll,” said Brink.