End of impasse over Polihali Dam construction bodes well for Gauteng

Loading player...
The good news was hidden in the jobs and tenders section of last week’s Lesotho Times. That’s where the Lesotho Highlands Development Authority (LHDA) announced the cancellation of prequalification for the construction of the Polihali Dam and transfer tunnel because it did not address “lenders’ requirements”. It will now go back to the beginning and put the project out to open tender, ending a year-long impasse over the procedure to be followed.

The Polihali Dam, Phase 2 of the Lesotho Highlands Water Project (LHWP), is critical to keep central SA water secure. It should have been finished this year. But because of delays in getting started, Gauteng and surrounding areas are now at risk of potentially calamitous water restrictions until at least 2026.

The LHDA said in its announcement that “the lenders came on board after the prequalification exercise had already commenced”, pointing a finger straight at the SA government. Financing is SA’s responsibility, but our ministers seemed more interested in extracting benefits from the project than ensuring it was implemented on time. The Trans-Caledon Tunnel Authority (TCTA), which successfully funded previous projects, will do the legwork. But it needs the minister and department of water & sanitation to take the lead and give direction. That ball was dropped.

Progress was delayed while then minister Nomvula Mokonyane tried to gain control over the process. She fired Zodwa Dlamini, the country’s chief delegate to the Lesotho Water Commission in Maseru, allegedly because Dlamini would not help one of Mokonyane’s pet companies, LTE, get a lucrative slice of the design contract. That LTE did not have the necessary capabilities (lamentably revealed on the much smaller, now infamous, Giyani water supply project) was no object.

The challenge now for water users in Gauteng and surrounds is to ensure Polihali does not become another Medupi, with political rent-seeking undermining the management of a complex and difficult project. So the other good news is that, because of its bilateral history, much of the project’s funding will come from international lenders — notably the African Development Bank and the New Development Bank. With the two governments, they will be looking over the shoulders of the LHDA. Repayment of their loans will be underpinned by the sale of water, so they need assurances that the project will be managed efficiently and honestly.

That’s very different to what happened with Eskom’s Medupi and Kusile power stations, which were ...
8 Sep 2020 9AM English South Africa Business News · News

Other recent episodes

Toyota Motors SA CEO Andrew Kirby

Business Day Senior Motoring correspondent Phuti Mpyane chats to Toyota Motors SA CEO Andrew Kirby about the threats to exports, tax and Chinese vehicles in SA.
24 Oct 2024 9AM 39 min

Ford injects R5bn into production of hybrid-electric bakkies

Business Day editor-in-chief Alexander Parker speaks to Ford Africa president Neale Hill about the company's decision to spend R5.2bn to turn its SA subsidiary into the only global manufacturer of plug-in, hybrid-electric Ranger bakkies.
8 Nov 2023 9AM 13 min

Digital innovation no longer up in the clouds

The Covid-19 pandemic is the ultimate catalyst for digital transformation and will greatly accelerate several trends already well under way before the pandemic. According to research by Vodafone, 71% of firms have made at least one new technology investment in direct response to the pandemic. This shows that businesses are…
13 Sep 2020 4PM 6 min